Construction Restarts on Wales' Rhyl Flats Windfarm

After construction delays last year, Industrial Info Resources (Sugar Land, TX) reports that turbine construction at the Rhyl Flats offshore windfarm off the north coast…

After construction delays last year, Industrial Info Resources (Sugar Land, TX) reports that turbine construction at the Rhyl Flats offshore windfarm off the north coast of Wales is set to restart.

RWE Innogy, part of large German utility RWE (Essen), has announced that construction of the first 25 wind turbines will begin when the jack-up barge Lisa-A has been loaded with components at the Welsh Port of Mostyn, from where it will sail to the windfarm site, which lies 5 miles offshore, the company said. The first of the 25 Siemens (Munich, Germany) SWT-107-3.6 wind turbines will be erected in a week after arrival and will be set onto one of 25 foundation piles that were sunk in 2008. Erection of the turbines was interrupted last October when the original KS Titan 1 jack-up vessel was lost in the Atlantic. It was being carried on the heavy-lift vessel MV Ancora, which ran into engine trouble before the Titan 1 capsized and sank.

The Lisa A will be joined by a replacement KS Titan 2 barge in the summer, supplied by Siemens Wind Power. To make up for lost time, turbine construction will run day and night at the 90-megawatt (MW) Rhyl Flats windfarm, which expects to be generating power by this summer and be fully operation in the fourth quarter. "The construction program to complete the second and final phase of Rhyl Flats Offshore Wind Farm is in place," says Richard Watson, Rhyl Flats project manager. "During the summer, the wind farm will start to produce its first electricity and we expect that all 25 wind turbines will be generating clean, green electricity in the final quarter of 2009."

Rhyl Flats is Wales' second offshore windfarm after North Hoyle, a 60 MW farm constructed in 2003. It was the U.K.'s first major offshore wind facility. RWE Innogy has been busy over the past year in the U.K. renewable market, and in December 2008 was given the green light to build and operate the massive 750-MW windfarm at Gwynt y Mor off the North Wales coast, one of the world's largest.

Subscribe to learn the latest in manufacturing.
Davi will provide industry knowledge and expertise to structural engineers.
In his new role, Kuhnle will focus on strengthening CERATIZIT’s engagement with the U.S. security and defense sector.
The company is a recognized supplier of sheet metalworking machinery, tooling, parts, and service to fabrication shops and manufacturers across the Mid-Atlantic.
Precision, repeatability, and process optimization are essential across all sectors of modern manufacturing. Whether producing hardened steel drivetrain components, aerospace-grade titanium structures, or complex parts…
The 5-flute solid carbide end mill is a workhorse for helical interpolation.

Sign Up For e-Newsletter

eNewsletter Signup
"
";s:6:"minnum";i:1;s:6:"maxnum";
Organized by SME
13 Apr
Mon, Apr 13, 2026 - 12:00 am
Thu, Apr 16, 2026 - 11:59 pm
415 Summer St., Boston, MA, United States, 02210
Organized by SME
14 Apr
Tue, Apr 14, 2026 - 12:00 am
Thu, Apr 16, 2026 - 11:59 pm
415 Summer St., Boston, MA, United States, 02210
Wed, Apr 22, 2026 - 12:00 am
Fri, Apr 24, 2026 - 11:59 pm
285 Andrew Young International Blvd NW, Atlanta, GA, United States, 30313
Sun, May 17, 2026 - 12:00 am
Thu, May 21, 2026 - 11:59 pm
601 Loyola Ave., New Orleans, LA, United States, 70113
Mon, Sep 14, 2026 - 12:00 am
Sat, Sep 19, 2026 - 11:59 pm
2301 S. Dr. Martin Luther King Jr. Drive, Chicago, IL, United States, 60616
Organized by SME
21 Oct
Wed, Oct 21, 2026 - 12:00 am
Fri, Oct 23, 2026 - 11:59 pm
3150 Paradise Road, Las Vegas, NV, United States, 89109
Tue, Nov 03, 2026 - 12:00 am
Fri, Nov 06, 2026 - 11:59 pm
3150 Paradise Road, Las Vegas, NV, United States, 89109
Organized by SME
11 May
Tue, May 11, 2027 - 12:00 am
Thu, May 13, 2027 - 11:59 pm
1305 Memorial Ave., West Springfield, Massachusetts, MA, United States